Project Number:
10022
St. Vincent Martyr School
St. Vincent Martyr School Media Center Renovation
Project Information:
Client:
Project Name:
Project Lead:
Project Description:
St. Vincent Martyr School
St. Vincent Martyr School Media Center Renovation
Hae-An Chyun
The scope of the project includes, but is not limited to, finish upgrades, a new interior storefront wall, built-in cabinets, new doors, and hardware, new ceilings and lighting
Bid Information:
DPMC Qualification:
Not Public Bid
Cost of Documents:
Bidding Requirements:
Bids will be accepted from a single general contractor for a lump sum bid as follows:
Schedule:
Drawings Available:
Friday, December 6, 2024
Pre-Bid Walkthrough:
Addendum:
Bids Due / Opening:
Thursday, December 12, 2024
Thursday, January 16, 2025
Commence Construction:
Substantial Completion:
Monday, May 19, 2025
Friday, August 15, 2025
Bidder's List:
Bidders | Address | Telephone |
---|
Bidders | Address | Telephone |
---|