Project Number:
9018MHS, GI
Montclair Township Board of Education
Curtain Wall Replacements @ Montclair High School and
George Inness High School Annex
Project Information:
Client:
Project Name:
Project Lead:
Project Description:
Montclair Township Board of Education
Curtain Wall Replacements @ Montclair High School and
George Inness High School Annex
William Ross
The scope of the project includes, but is not limited to, replacement of select curtain wall systems at Montclair High School, and replacement of the cafeteria curtain wall system at George Inness High School Annex. The Contract Documents define the full project scope.
Bid Information:
DPMC Qualification:
(C008) GENERAL CONSTRUCTION
(C009) GENERAL CONSTRUCTION / ALTERATIONS / ADDITIONS
Cost of Documents:
Bidding Requirements:
Bids will be accepted from a single general contractor for a lump sum bid as follows:
Schedule:
Drawings Available:
Friday, September 20, 2024
Pre-Bid Walkthrough:
Addendum:
Bids Due / Opening:
Wednesday, September 25, 2024 at 11:00 AM at 100 Chestnut Street, Montclair, NJ
07042
Friday, October 18, 2024 at 11:00AM at 22 Valley Road, Montclair, NJ 07042
Commence Construction:
Substantial Completion:
Thursday, June 19, 2025
Friday, August 29, 2025
Bidder's List:
Bidders | Address | Telephone |
---|
Bidders | Address | Telephone |
---|