Project Number:

9420

Morris School District

Boiler Replacement @ Frelinghuysen Middle School

Project Information:

Client:

Project Name:

Project Lead:

Project Description:

Morris School District

Boiler Replacement @ Frelinghuysen Middle School

Hae-An Chyun

The scope of the project includes, but is not limited to, the removal and replacement of the existing hot water boilers with new boilers to meet the building capacity at Frelinghuysen Middle School. Existing boiler controls, burners, breeching and all associated components, etc. will be replaced. New boiler controls will be integrated into the building automation system. Existing distribution piping will be modified as needed to connect the new equipment. Existing lighting will be replaced as necessary for code compliance. The boiler room will also receive new finishes on the floors and walls.

Bid Information:

DPMC Qualification:

(C032) HVACR or
(C033) BOILERS
(C030) PLUMBING
(C047) ELECTRICAL

Cost of Documents:

Bidding Requirements:

Bids will be accepted from a single general contractor for a lump sum bid as follows:

Schedule:

Drawings Available:

Friday, November 8, 2024

Pre-Bid Walkthrough:

Addendum:

Bids Due / Opening:

Wednesday, November 13, 2024 at 1:30pm at 10 Jane Way, Morristown NJ 07960

Thursday, December 12, 2024 at 10:00am at 31 Hazel St, Morristown, NJ 07960

Commence Construction:

Substantial Completion:

Friday, June 20, 2025

Friday, August 22, 2025

Bidder's List:

Bidders
Address
Telephone
Bidders
Address
Telephone