Project Number:
9526 / 9528
Millburn Board of Education
Rod Grant Boiler Replacements & HV Upgrades at Wyoming ES
/ Boiler Replacement @ The Millburn Board of Education
Project Information:
Client:
Project Name:
Project Lead:
Project Description:
Millburn Board of Education
Rod Grant Boiler Replacements & HV Upgrades at Wyoming ES
/ Boiler Replacement @ The Millburn Board of Education
Caitlyn Adames
The scope of work for this project includes, but is not limited to, replacement of an existing boiler, and replacement of heating units within certain classrooms and associated controls at Wyoming ES and the
replacement of antiquated boilers; (2) two boilers in the Original Wing, & (2) two boilers in the Science Wing at Millburn HS.
Bid Information:
DPMC Qualification:
(C032) HVACR (C030) PLUMBING
(C047) ELECTRICAL
Cost of Documents:
Bidding Requirements:
Bids will be accepted from a single general contractor for a lump sum bid only.
Schedule:
Drawings Available:
Monday, November 18th, 2024
Pre-Bid Walkthrough:
Addendum:
Bids Due / Opening:
Wednesday, November 20th, 2024
Tuesday, December 10th, 2024 @2:00pm
Commence Construction:
Substantial Completion:
Monday, May 5th, 2025
Friday, August 15th, 2025
Bidder's List:
Bidders | Address | Telephone |
---|
Bidders | Address | Telephone |
---|